The vessel has been filled and prepared through the calibration process, but before it goes live, control needs to be transferred to CEMEX.
The transfer of control process normally takes around 2 weeks. |
Week 1 - Begin transfer of transparent data between customer and CEMEX Customer Services.
Week 2 - CEMEX Customer Services closely facilitate with customer to build better data and gain increasing confidence.
End of week 2 - Complete handover of cement delivery process to CEMEX Customer Services.
If you have any questions about this or anything relating to Smart SiloTM please contact us on 0800 353 433.
|
 |


|